Facilities Design and Construction (FD&C)
Page Navigation
- Facilities Design & Construction (FD&C)
- Staff and Organizational Chart
- PAE Handbook and Design Criteria
- School Ed Specs
- Building Permit Application
- Current Major Building Projects
-
Completed Projects
- 2019 Cypress Woods Elementary School
- 2019 Lakewood High School
- 2020 Melrose Elementary School
- 2020 Pinellas Park Middle School
- 2020 Tarpon Springs High School
- 2021 North Shore Elementary School
- 2021 Northeast High School
- 2021 Richard O. Jacobson Technical High School at Seminole
- 2021 San Jose Elementary School
- 2021 Sanderlin IB K-8 School
- 2021 Sawgrass Lake Elementary School
- 2021 Shore Acres Elementary School
- 2022 Coachman Service Center
- 2022 Orange Grove Elementary School
- 2022 St. Petersburg High School
- 2023 Clearwater High School
- 2023 Lakewood High School
- 2023 Mangrove Bay Middle School
- 2023 Midtown Academy
- 2023 Mildred Helms Elementary School
- 2023 Pinellas Central Elementary School
- 2023 Seventy-Fourth St. Elementary School
- 2023 Tyrone Middle School
- 2024 Gibbs High School
- 2024 Gulf Beaches Elementary School
- 2024 Sandy Lane Elementary School
Cypress Woods Elementary - New 12 Classroom Addition
-
Updated 08/24/20
Project information:
Architect: Renker-Eich-Parks
Contractor: Charles Perry Partners, Inc. (CPPI)
PCSB Project Manager: Bruce Stott
Project Budget: $5.9 Million
Start Date: December 2018
Completion: October 2019
Construction/Renovation of:
- Removal of temporary classrooms that are currently on site
- Construction of a new 12 classroom wing
- Upgrade intrusion system campus wide
- Redesign of the existing bus loop and walkway canopies to accommodate the new classroom building
- New fire line and connection to the right-of-way in front of campus
Work Progress:
- Final Inspection of Punch List/Warranty Items scheduled for 7/27/20
- Project is complete