Pinellas Park Middle School - Major Renovations Campus Wide

  • Updated on 08/24/20

    Project information:

    Architect: Harvard Jolly Inc

    Contractor:  Walbridge Aldinger LLC

    PCSB Project Manager: Mike Parkinson

    Project Budget: $35 Million

    Start Date: September 2017

    Completion: April 2020

     

    Construction/Renovation of:

    • Demolish Buildings 1, 2, 6, 7, 8, and 10 and Rebuild with new multiuse
      building
    • New Administration and Student Services building (estimated 41,025 gross square feet)
      • Art room
      • Media center
      • 16 classroom
    • Renovate the gym and cafeteria (Building 9) (estimated 29,000 square feet)
      • Roof replacement
      • New Paint
      • New HVAC
      • Refinish Gym Floor
      • Expansion of cafeteria
    • Renovate the new science building (Building5) (estimated 8,800 square feet)
      • Building 5 would get updated with new ceilings, lights, and paint.
      • New HVAC
      • Update the science rooms emergency shut off
    • Renovate classroom Buildings 3 (estimated 25,800 square feet), and 4 (estimated 25,800 square feet)
    • Upgrade the chiller to accommodate new 4 pipe system for
      entire campus.
    • New bus loop and adding teacher/parent parking
    • New retention pond
    • New track on west side of property
    • New Basketball and Baseball Fields

    Project status:

    • In closeout
    • Project is Complete